Lowering the Axles - raising the trailer
This procedure is erroneously referred to as
"flipping the axles".
The axles are not inverted or flipped over, but are re-positioned from
over to under the springs. This will lift the trailer about 4 to 5
inches. This series of pictures details the installation of the Dexter
axle kit - no welding involved!
The "before" ... the owner wants to raise this
trailer 4 to 5 inches for more road clearance. A Dexter Axle kit will
be used ...
This is the contents of one axle kit ...
The trailer is jacked up and placed on jack
stands. This allows the axles to hang freely so that the work can
proceed.
Proper equipment is an absolute must!
This is the original configuration of the axles.
The springs are mounted below the axle tubes. The project is to raise
the trailer by re-positioning the axles so that the springs are located
over the axle tubes thus raising the trailer by 3 to 4 inches ...
The old u-bolts removed and the front spring
hanger nut removed ... cut the brake wires at this point to prevent
accidentally tearing them out and damaging the brake magnets ...
Bolts removed, axle is ready to be dropped. The
axle is resting on a floor jack placed in the center of the axle tube
...
This shows the front axle dropped to the floor and
rolled ahead ...
... so that the spring can be re-installed above
it. The axle is then rolled back under the spring ...
... and the kit with the new u-bolt, saddle and
mounting plate are assembled in place ...
The finished job ...
The trailer has been raised 4 inches ...
|